The Taliban claimed that construction work on the Turkmenistan-Afghanistan-Pakistan-India (TAPI) gas pipeline project in Herat is progressing rapidly, and that the section of the project in the province is scheduled to be completed and ready for operation by the end of 2026.
Baktiar News Agency, which is controlled by the Taliban, reported on Tuesday, August 29, 2026, that 145 kilometers of the 153-kilometer TAPI project route in Herat have so far been leveled and prepared.
According to the report, pipeline installation has been completed along 120 kilometers of the route, while 128 kilometers of an inspection road have also been constructed.
The Taliban’s Ministry of Mines and Petroleum said that 87 kilometers of trenches have been excavated for burying the pipeline, and 51 kilometers of pipeline have been buried underground.
The Taliban said that, in cooperation with Turkmenistan’s Turkmen Gas company, the design of the gas distribution network in Herat has begun, and fieldwork is scheduled to start soon.
According to the report, construction of a 22-kilometer branch gas transmission line with a diameter of 20 inches is scheduled to begin. The line will have the capacity to transmit and regulate 8.8 million cubic meters of gas per day and 3.2 billion cubic meters annually.